Completed (2022-10-27, 07:35) - ID-NET team confirmed end of maintenance. Systems are up and running.
Update (2022-10-27, 07:30) - ETx router switchover to the new hardware has been done, systems outside ETx zone need more time to recover from the switch.
Update (2022-10-27, 07:20) - Switchover to the new ETx router is delayed
Maintenance (2022-10-27, 06:30) - ID-NET team is starting with the planned update of the ETx router.
Info (2022-10-24, 11:06) - On Thursday, October 27 2022 from 06:30 to 07:00, the new router hardware in the network zone ETx will be commissioned. Affected by this interruption is the entire data network, wireless and IP telephony in the following buildings:
Last updated: Monday, September 2, 2024 at 07:21